News

10 February 2022 - Quarterly groundwater monitoring

Groundwater monitoring results demonstrated mass removal by MPE and the in-situ biodegradation. Due to a low efficiency of the MPE system, the active remediation was stopped in November 2020. Quarterly groundwater monitoring was continued. The results showed further in-situ biodegradation of volatile chlorinated compounds reducing the contaminant spreading risks.

 

06 December 2019 - Extension of the multiphase extraction system

3 extraction wells are installed in december 2019 in the tankpark (near excavation zone, near loading area at well P465 and at small plume area) in order to improve MPE system

 

09 November 2019 - Remediation by multiphase extraction

In situ chemical oxidation stopped and the installation (ozone generator) and perozone injection system is removed.   All zones are remediated by multiphase extraction lowering groundwater till 3 m-bgl in the period november 2018 - november 2019.

 

07 October 2019 -

The 15th groundwater monitoring is performed in October 2019.

 

08 November 2018 - Remediation by multiphase extraction and in-situ chemical oxidation

The loading zone at well P465 continued to be remediated by in-situ chemical oxidation using perozone.  At the other zones (excavation zone, small plume and large plume at the tank park), remediation using multiphase extraction is executed by lowering groundwater till 1.8 m-gl in the periode of December 2017 - November 2018

Read more...

 

08 December 2017 - Multiphase extraction test

The Life project proved that in-situ chemical oxidation is very effective in migration zones but not in source zones of the VOPAK site. Therefore, a multi-phase extraction test in the zones was performed between 13 July and 8 December 2017 to evaluate this technique. Contaminant mass concentration in the extracted air diminished from 175 ppm to 22 ppm (using PID detector 10.6 eV).

 

31 August 2017 - Final documents of the LIFE project available in the publication list

Final documents of the LIFE project available in the publication list

  • Final H&S procedures of the LIFE project
  • Feasibility, benefits and multi-criteria analyses of ISCO using perozone
  • Laymen’s report with final conclusion of the LIFE project

Read more...

 

31 August 2017 - LIFE ends in August 2017

LIFE project ends in August 2017 but not the soil remediation works. News remains updated

 

08 May 2017 - 11th groundwater monitoring event groundwater monitoring results

The monitoring results and evaluation of the 11th monitoring event in April 2017 are available.

Read more...

 

26 April 2017 - 11th groundwater monitoring event

A new groundwater monitoring is performed about mote then a year after the start-up of the remediation of the big source area in the tankfarm.  The monitoring results and evaluation will be available soon. 

Read more...

 

03 April 2017 - Next phase civil works in the tankfarm

Read more...

01 March 2017 - 10th groundwater monitoring event groundwater monitoring results

Read more...

07 February 2017 - 10th groundwater monitoring event

Read more...

07 November 2016 - Installation restarted

Read more...

28 October 2016 - 9th groundwater monitoring event monitoring results

Read more...

06 October 2016 - Civil works in the tankfarm

Read more...

06 October 2016 - 9th groundwater monitoring event

Read more...

19 August 2016 - Evaluation of perozone injections

Read more...

01 July 2016 - Groundwater monitoring results 8th monitoring

Read more...

15 June 2016 - 8th groundwater monitoring event

Read more...

15 March 2016 - Groundwater monitoring results 7th monitoring

Read more...

18 February 2016 - 7th groundwater monitoring event

Read more...

06 January 2016 - Start of the in situ remediation in the big source area in the tank farm

Read more...

11 December 2015 - LIFE+ project experience discussed by environmental VOPAK representatives and RSK soil remediation experts of the Netherlands and Belgium

Read more...

31 October 2015 - Groundwater monitoring results

Read more...

12 October 2015 - 6th groundwater monitoring event

Read more...

10 August 2015 - Preparation of the in situ remediation in the big source area in the tank farm

Read more...

22 July 2015 - Evaluation of perozone injections in the tank farm

Read more...

12 June 2015 - Project presentation at Aquaconsoil in Copenhagen, Denmark

Read more...

06 June 2015 - Groundwater monitoring results

Read more...

29 May 2015 - Leakage in aboveground hydrogen peroxide pipe

Read more...

11 May 2015 - 5th groundwater monitoring event

Read more...

29 April 2015 - Fine tuning extraction system

Read more...

13 March 2015 - Start of the in situ remediation in the small source area in the tank farm

Read more...

05 March 2015 - Preparation of the in situ remediation in the small source area in the tank farm.

Read more...

27 February 2015 - Installation restarted

Read more...

17 February 2015 - Monitoring results December 2014

Read more...

21 January 2015 - Reason Ozone odour near the ISCO installation identified

Read more...

07 January 2015 - Ozone odor near the ISCO installation

Read more...

17 December 2014 - Groundwater monitoring in the midway and tank farm

Read more...

10 December 2014 - Installation soil vapor monitoring system around storage tanks

Read more...

18 September 2014 - Groundwater monitoring in the Midway

Read more...

05 August 2014 - Project presentation at conference in Finland

Read more...

01 August 2014 - ISCO temporarily stopped

Read more...

26 June 2014 - Repair of monitoring well covers

Read more...

19 June 2014 - ISCO restarted

Read more...

30 May 2014 - Concrete floor renewed

Read more...

15 May 2014 - New injection regimes based on field tests

Read more...

28 February 2014 - Ozone injections temporarily stopped

Read more...

31 January 2014 - ISCO shut down due to ozone odour

Read more...

30 January 2014 - Encouraging monitoring results

Read more...

29 November 2013 - Second phase of in situ remediation started

Read more...

28 November 2013 - First phase of in situ remediation successfully completed

Read more...

31 October 2013 - Remediation goals reached in former drum storage area

Read more...

11 October 2013 - MPE definitely shut down

Read more...

30 September 2013 - First monitoring results available

Read more...

26 July 2013 - MPE shut down

Read more...

04 April 2013 - In situ remediation started

Read more...

26 March 2013 - Site visit for stakeholders

Read more...

18 March 2013 - Injection and extraction system installed

Read more...

11 December 2012 - Excavation works executed

Read more...

14 September 2012 - Remediation works started!

Read more...

28 October 2011 - RAP approved

Read more...

08 July 2011 - RAP submitted

Read more...

01 April 2011 - Pilot test completed

Read more...

Life

Our Partners

Coordinating beneficiary

Vopak

Associated beneficiary

RSK Group PLC

Badeco

Progress

First phase of in-situ remediation completed. Second phase of in-situ remediation on-going, ISCO and SVE operational.